Apply Job Order And Process Costing

Help Questions

CPA Business Analysis and Reporting (BAR) › Apply Job Order And Process Costing

Questions 1 - 10
1

Pinecrest Manufacturing uses job-order costing with a predetermined overhead rate of $15 per direct labor hour. Job #312 incurred direct materials of $4,200, direct labor of 180 hours at $20 per hour, and used 180 direct labor hours for overhead application. What is the total cost of Job #312?

$11,700

$7,800

$10,500

$9,300

Explanation

Direct labor cost = 180 hours x $20 = $3,600. Applied overhead = 180 hours x $15 = $2,700. Total job cost = $4,200 + $3,600 + $2,700 = $10,500. Option A omits applied overhead entirely. Option C applies only part of the overhead. Option D applies an overhead rate higher than the predetermined rate.

2

Pinecrest Manufacturing has budgeted manufacturing overhead of $360,000 and budgeted direct labor hours of 24,000 for the year. What is the predetermined overhead rate?

$12.00 per DLH

$18.00 per DLH

$24.00 per DLH

$15.00 per DLH

Explanation

Predetermined overhead rate = Budgeted overhead / Budgeted activity = $360,000 / 24,000 = $15.00 per DLH. Option A divides by 15,000 hours. Option B divides by 20,000 hours. Option D divides by 30,000 hours.

3

Pinecrest Manufacturing applies overhead at $15 per direct labor hour. During the year, actual direct labor hours were 22,000 and actual overhead incurred was $345,000. What is the amount and direction of under- or overapplied overhead?

$30,000 underapplied

$30,000 overapplied

$15,000 overapplied

$15,000 underapplied

Explanation

Applied overhead = 22,000 DLH x $15 = $330,000. Under/overapplied = Actual - Applied = $345,000 - $330,000 = $15,000 underapplied. Actual overhead exceeded applied overhead, so overhead was underapplied. Option A has the correct amount but incorrect direction. Option B uses incorrect applied overhead in the calculation. Option C has both an incorrect amount and incorrect direction.

4

Pinecrest Manufacturing reports: beginning WIP $45,000, direct materials added $280,000, direct labor $195,000, overhead applied $165,000, ending WIP $62,000. What is the cost of goods manufactured for the period?

$578,000

$623,000

$685,000

$640,000

Explanation

Cost of goods manufactured = Beginning WIP + Direct materials + Direct labor + Overhead applied - Ending WIP = $45,000 + $280,000 + $195,000 + $165,000 - $62,000 = $623,000. Option B omits the deduction for ending WIP. Option C omits beginning WIP from the calculation. Option D applies an incorrect ending WIP balance.

5

Riverdale Co. has total conversion costs to account for of $280,000 and equivalent units of production for conversion of 20,000. What is the cost per equivalent unit for conversion costs?

$12.00

$14.00

$15.50

$16.00

Explanation

Cost per equivalent unit = Total conversion costs / EUP = $280,000 / 20,000 = $14.00. Option A divides by an incorrect equivalent unit count of approximately 23,333. Option B and Option C result from arithmetic errors using incorrect denominators.

6

Riverdale Co. has total direct materials costs of $396,000. Materials are added at the start of the process, so ending WIP is 100% complete for materials. Units completed and transferred: 18,000; ending WIP: 4,000 units. What is the cost per equivalent unit for direct materials?

$16.00

$18.00

$20.00

$22.00

Explanation

EUP for materials = 18,000 + (4,000 x 100%) = 22,000. Cost per EU for materials = $396,000 / 22,000 = $18.00. Option B divides by 24,750, overstating equivalent units. Option C divides by 19,800. Option D divides by 18,000, treating ending WIP as having zero material content.

7

Riverdale Co. has a cost per equivalent unit of $18.00 for materials and $14.00 for conversion. What is the total cost assigned to the 18,000 units completed and transferred out?

$252,000

$630,000

$576,000

$504,000

Explanation

Cost per completed unit = $18.00 + $14.00 = $32.00. Total cost transferred = 18,000 x $32.00 = $576,000. Option A applies only the conversion cost rate to all 18,000 units. Option C applies only the materials rate to all units. Option D applies an incorrectly higher combined rate.

8

Riverdale Co. has cost per EU: materials $18.00, conversion $14.00. Ending WIP is 4,000 units (100% complete for materials, 50% complete for conversion). What is the total cost assigned to ending WIP?

$100,000

$128,000

$72,000

$56,000

Explanation

Materials cost in ending WIP = 4,000 x 100% x $18.00 = $72,000. Conversion cost in ending WIP = 4,000 x 50% x $14.00 = $28,000. Total ending WIP cost = $72,000 + $28,000 = $100,000. Option A treats ending WIP as 100% complete for conversion as well. Option B includes only the materials component. Option D includes only the conversion component.

9

A company uses job-order costing. Job #445 had a beginning balance of $8,500. During the month, direct materials of $6,200 were requisitioned, 80 direct labor hours were worked at $25 per hour, and overhead is applied at $18 per direct labor hour. What is the ending balance on Job #445's cost sheet?

$16,700

$18,140

$19,580

$17,560

Explanation

Direct labor = 80 hours x $25 = $2,000. Applied overhead = 80 hours x $18 = $1,440. Ending balance = $8,500 + $6,200 + $2,000 + $1,440 = $18,140. Option A omits applied overhead. Option B applies an incorrect overhead rate. Option C applies overhead to the beginning balance as well as current hours.

10

Using the FIFO process costing data: current period conversion costs $189,000 and FIFO equivalent units for conversion of 21,000. What is the cost per equivalent unit for conversion under FIFO?

$8.00 per equivalent unit

$7.50 per equivalent unit

$9.00 per equivalent unit

$10.00 per equivalent unit

Explanation

Under FIFO, cost per EU = Current period costs only / FIFO equivalent units = $189,000 / 21,000 = $9.00. FIFO excludes beginning WIP costs from the rate calculation, preserving the prior-period cost in the beginning WIP layer. Option A divides by 23,625. Option C divides by 18,900. Option D divides by 25,200.

Page 1 of 3