Under the Restatement (Second), when is a liquidated damages clause enforceable?
Tap card or press Space to flip
When the amount is reasonable in light of the anticipated or actual loss and the difficulty of proving loss. Reasonableness may be measured either at formation or by the loss actually caused.
1 / 10
This deck focuses on Liquidated Damages And Penalties, giving you a quick way to review the definitions, rules, and examples that matter most for Bar Exam (Next Generation).
Work through these flashcards in short sessions. Try to answer each prompt before flipping the card, then revisit any cards you miss until the explanation feels automatic.
Free account · cards you mark are saved to it