What this quiz covers
This quiz focuses on Assigning Costs To Jobs, giving you a quick way to practice the rules, question types, and explanations that matter most for Cost Accounting.
Job #12 was completed with a total cost of $5,000. It was immediately sold to the customer on account for $7,500.
Which of the following journal entries correctly records the transfer of Job #12 from work in process to its next stage upon completion?
Cost Accounting Quiz
Practice Assigning Costs To Jobs in Cost Accounting with focused quiz questions that help you check what you know, review explanations, and build confidence with test-style prompts.
This quiz focuses on Assigning Costs To Jobs, giving you a quick way to practice the rules, question types, and explanations that matter most for Cost Accounting.
Try each quiz question before looking at the correct answer. Use the explanations to review missed ideas, then come back to similar questions until the pattern feels familiar.
Job #12 was completed with a total cost of $5,000. It was immediately sold to the customer on account for $7,500.
Which of the following journal entries correctly records the transfer of Job #12 from work in process to its next stage upon completion?
A product, Job #Alpha, is processed through two sequential departments. In Department 1 (Molding), it incurred $2,000 in direct materials and $800 in direct labor. Overhead in Dept. 1 is applied at 150% of direct labor cost. The job was then transferred to Department 2 (Finishing). In Dept. 2, it incurred an additional $600 in direct labor, and overhead was applied at a rate of $30 per machine hour for the 20 hours it spent in the department.
What is the total manufacturing cost of Job #Alpha upon its completion?
The job cost sheet for Job #777, the only job in process at the end of the month, shows a total cost of $35,000. Direct materials charged to the job were $11,000, and direct labor was 500 hours at a rate of $24 per hour. The company applies manufacturing overhead on the basis of direct labor hours.
What is the company's predetermined overhead rate per direct labor hour?
A custom cabinet job (Job #3C) incurred costs of $2,500. During final inspection, a flaw was discovered that rendered the cabinet unsellable. The cost of this spoiled unit is considered abnormal because it resulted from an employee's gross negligence. The cabinet has a disposal value of $100.
How does the spoilage of Job #3C affect the total cost recorded for that specific job?
A consulting firm applies overhead to client jobs at 125% of direct professional labor cost. For a particular audit engagement, the total conversion cost was recorded as $90,000. Direct materials costs for the engagement were negligible.
What was the amount of direct professional labor cost assigned to this engagement?
A boat manufacturer is building a custom yacht, Job #Y-01. A special type of teak wood was purchased specifically for this job from an overseas supplier. The supplier's invoice was for $25,000. Additional costs incurred were $1,500 for international shipping (freight-in) and $500 for import duties. The company's policy is to treat all costs necessary to acquire direct materials as part of the direct material cost.
What is the total direct material cost that should be assigned to Job #Y-01 from this purchase?
The total manufacturing cost assigned to Job #215 was $48,000. The company applies manufacturing overhead at a rate of 150% of direct labor cost. The job was charged with $12,000 in direct labor cost.
What was the amount of direct materials cost assigned to Job #215?
At the beginning of the month, the job cost sheet for Job #410 showed a balance of $8,500. During the month, the job incurred an additional $4,000 in direct material costs and 200 hours of direct labor at a rate of $22 per hour. Manufacturing overhead was applied at a rate of $10 per direct labor hour. The job was not completed by the end of the month.
What is the balance on the job cost sheet for Job #410 at the end of the month?
A manufacturing company uses a job-order costing system. For Job #B-52, the following costs were incurred: direct materials requisitioned of $15,000, indirect materials of $2,000, direct labor of 400 hours at $25 per hour, and indirect labor of $3,000. The company applies manufacturing overhead to jobs at a rate of 120% of direct labor cost.
What is the total manufacturing cost assigned to Job #B-52?
During production of Job #M-16, the production supervisor submitted a materials requisition for $7,000 of component parts and $500 of machine lubricants. Later, it was discovered that $800 of the component parts were not needed for the job and were returned to the storeroom.
What is the total direct materials cost that should be recorded on the job cost sheet for Job #M-16?
A specialty furniture maker is producing a custom dining table (Job #C-88). The total cost incurred prior to inspection is $3,000. Upon inspection, it was discovered that a portion of the table was defective due to a machine malfunction. The cost to rework the defect was $400. Separately, the customer requested a change to the design, which resulted in $200 of rework costs.
What is the total cost that should be assigned to Job #C-88 after accounting for the rework?
For the year, Apex Manufacturing estimated total overhead costs of $500,000 and 25,000 total machine hours. In March, Job #M-03 was started and completed, consuming 120 machine hours. At the end of the year, actual total overhead was $520,000 and actual machine hours were 26,000.
What amount of manufacturing overhead was assigned to Job #M-03 during March?
Alpha Corp. produces custom machinery and uses a job-order costing system with two production departments: Machining and Assembly. The predetermined overhead rate in Machining is $20 per machine-hour, and in Assembly, it is $15 per direct labor-hour. Job #77 passed through both departments. Data for Job #77 are as follows:
What is the total amount of manufacturing overhead applied to Job #77?
An architecture firm uses a job-order costing system for its projects. For the 'Downtown Tower' project, costs were as follows: Senior Architect labor, $40,000; Junior Architect labor, $25,000; travel and blueprinting costs directly for the project, $8,000. Firm-wide administrative and support overhead is applied to projects at a rate of 60% of total direct professional labor cost.
What is the total cost assigned to the 'Downtown Tower' project?
A company currently applies overhead using a plantwide rate of $40 per direct labor-hour. It is considering a switch to a departmental rate system. For Job #K-10, the following data is available: it required 10 direct labor-hours in Department A and 5 direct labor-hours in Department B. The new proposed departmental overhead rates are $25 per direct labor-hour for Department A and $70 per direct labor-hour for Department B.
By how much would the total cost assigned to Job #K-10 change if the company switches to the departmental overhead rates?
A print shop completed Job #P-34. The job cost sheet shows direct materials of $1,200, direct labor of $1,800, and applied manufacturing overhead of $900. The company prices its jobs at a 40% markup on total manufacturing cost.
What is the selling price for Job #P-34?
An employee, who earns a regular wage of $20 per hour and an overtime rate of $30 per hour, worked on Job #R-99. The overtime was required to meet a tight deadline specifically requested by this customer. The employee's time ticket shows 40 regular hours and 5 overtime hours were charged to Job #R-99.
What is the total direct labor cost that should be assigned to Job #R-99?
A custom fabrication job, #F-08, required 30 hours of work from a senior welder at $35 per hour and 50 hours from a junior fabricator at $20 per hour. The company applies manufacturing overhead at 75% of total direct labor cost. Direct materials for the job totaled $4,500.
What is the total manufacturing cost of Job #F-08?
A company's records show that total manufacturing overhead applied during the year was $300,000. The predetermined overhead rate was calculated based on direct labor cost. Job #A-45, completed during the year, incurred $12,000 in direct materials and $15,000 in direct labor cost. The total direct labor cost for all jobs during the year was $250,000.
What is the total manufacturing cost of Job #A-45?
A direct laborer working on Job #A-12 earns $24 per hour. During an 8-hour shift, an unexpected power outage caused all machinery to stop for 1.5 hours. For the entire shift, the company's policy considers 0.5 hours to be normal idle time for breaks and personal needs, which is included in the predetermined overhead rate.
How should the labor cost for the 2 hours of total idle time (1.5 for outage, 0.5 for breaks) be allocated?