A manufacturer is choosing between two sampling plans to decide whether to hold a batch for rework. Historically, 10% of batches are truly defective.
Plan A:
- If a batch is defective, the sample triggers a hold 80% of the time.
- If a batch is not defective, the sample still triggers a hold 5% of the time.
Plan B:
- If a batch is defective, the sample triggers a hold 60% of the time.
- If a batch is not defective, the sample triggers a hold 1% of the time.
The manager's goal is to minimize the probability that a batch released (not held) is actually defective.
Which strategy is most reasonable given the probabilities?
YOUR PROGRESS
20
QUESTIONS
Ready when you are
Answer in any order. Your progress shows here as you go.
QUESTIONS
KEYBOARD
Pick an answer ABCD
Next question ↵→
Previous ←
Flag for review F
Answers save as you go · flagged questions come back at the end