01 / 20

Apply Time Value
of Money Concepts

Master future value, present value, NPV, and IRR to compare investments across time.

Series 65

Money Has a Time Value

A dollar today is worth more than a dollar tomorrow. Why? Because money you hold now can be invested to earn interest, so it grows over time.

Four Key Terms

Future Value (FV)
What an amount today grows to after earning interest.
Present Value (PV)
What a future amount is worth today, discounted back.
NPV
Net Present Value: PV of all cash flows minus the cost.
IRR
Internal Rate of Return: the rate that makes NPV equal zero.

Visualizing the Timeline

Year 0 Year 1 Year 2 Year 3 PV discount FV grow Discounting moves money backward; compounding moves it forward

The Future Value Formula

To grow a present amount forward, multiply by one plus the rate, raised to the number of periods:

The Present Value Formula

Present value is simply the future value formula rearranged: divide instead of multiply to discount a future amount back to today.

NPV and IRR

The NPV Decision Rule

1
If \( NPV > 0 \): accept. The investment adds value above its cost.
2
If \( NPV = 0 \): indifferent. It exactly meets the required return.
3
If \( NPV < 0 \): reject. It destroys value relative to alternatives.

NPV vs IRR

Both evaluate the same cash flows, but they answer different questions.

NPV answers
"How much dollar value does this add?" Expressed in dollars.
IRR answers
"What annual return does this earn?" Expressed as a percent.

How to Apply It

1
List the cash flows. Identify each amount and the period it occurs in.
2
Choose a discount rate. Use the required return or opportunity cost.
3
Discount each flow to present value with \( PV = \frac{FV}{(1+r)^n} \).
4
Sum and subtract cost. Apply the NPV rule to decide.

Example 1: Future Value

You invest $1,000 at 6% annually for 3 years. What is its future value?

Example 2: Present Value

A bond pays $5,000 in 4 years. At an 8% discount rate, what is it worth today?

Example 3: NPV

A project costs $1,000 and returns $600 in year 1 and $700 in year 2. Discount rate is 10%.

Common Mistakes

✕ Wrong period count
Using annual rate with monthly periods, or miscounting \( n \).
✕ Forgetting the cost
Summing PVs but not subtracting the initial outlay in NPV.
✕ Confusing PV and FV
Multiplying when you should discount, or vice versa.
✕ Ignoring the discount rate
A higher rate lowers PV; using the wrong rate flips the decision.

Concept Summary

Answers Decision
Future Value Grown amount Plan for growth
Present Value Worth today Set a fair price
NPV Dollar value added Accept if \( > 0 \)
IRR Annual return % Accept if \( > \text{hurdle} \)

Question 1 of 5

Why is $1 today worth more than $1 received next year?

Question 2 of 5

What is the future value of $2,000 invested at 5% for 2 years?

Question 3 of 5

Under the NPV rule, you should accept a project when:

Question 4 of 5

The IRR of an investment is the discount rate at which:

Question 5 of 5

A payment of $1,100 due in 1 year is discounted at 10%. Its present value is: