PASSAGE
A renovation contract specified that all interior doors be solid-core oak. To cut costs, the contractor ordered hollow-core doors with oak veneer and installed them, saving $6,000. The doors look identical, are fully functional, and have the same fire rating; replacing them would cost $10,000. The owner discovered the substitution after the final payment was due and refused to pay the remaining $30,000.
In the contractor's action for the remaining contract price, which statement is most accurate?