CONTRACTS
Question 1 of 12
No time limit
Current
Answered
Flagged
Not seen
PASSAGE
O owns a vacant lot and hires G, a general contractor, to build a house for $400,000. During excavation, G strikes a massive underground granite ledge that a soil report commissioned by O had indicated would not be present. Removing it will cost an additional $40,000. G tells O he will stop work unless O agrees to pay an extra $40,000. O, anxious to complete the project, signs a written modification promising to pay the extra amount. After the house is completed, O refuses to pay the $40,000. G sues.
Is G entitled to recover the additional $40,000?