- Which of the following is the developer's best argument for enforcing the clause?
Answer: The $4,000 per-day amount was a reasonable forecast of the probable loss at the time of contracting, and actual damages need not be proven.
A liquidated damages clause is enforceable if, at the time of contracting, damages were difficult to estimate and the amount fixed was a reasonable forecast of just compensation. Here, the parties identified difficulty of proof, and $4,000 per day was within the $3,500-$5,000 range projected before the breach. The fact that provable damages turned out lower does not make the clause a penalty; validity is assessed primarily at formation, and actual loss is only evidence of reasonableness. A is wrong because a party's characterization is not conclusive. B is wrong because a valid liquidated damages clause is not merely a ceiling; it fixes the exclusive amount. C is wrong because the anticipated range for a 25-day delay was $87,500-$125,000, not $40,000.
- How much can the restaurant owner recover from the contractor?
Answer: $5,000, because the enforceable liquidated damages clause fixes the exclusive measure of damages even though it undercompensates the owner.
The penalty doctrine polices only amounts that are unreasonably large; it does not invalidate a liquidated damages clause merely because it turns out to undercompensate. Because the $500 figure was a reasonable forecast at formation and the loss was difficult to estimate, the clause is enforceable and exclusive. The owner cannot recover the higher actual loss. A and B incorrectly treat undercompensation as a penalty. D is wrong because willfulness does not allow a court to rewrite a valid liquidated damages clause.
- If the buyer sues to recover the deposit, what is the likely result?
Answer: Seller retains $40,000 and must refund $460,000 because the liquidated amount is grossly disproportionate to the seller's actual loss and is a penalty.
Liquidated damages are allowed in real estate sales, but the amount must be a reasonable forecast of loss and not a penalty. Here the seller kept a 25% deposit ($500,000) while its actual loss was only $40,000 (the $20,000 resale shortfall plus $20,000 costs). The enormous disparity shows the forfeiture was punitive, not compensatory. Because the clause is a penalty, the buyer may recover the excess over actual loss. A and B ignore the unreasonableness and the form-contract nature. C is wrong because real estate contracts may include valid liquidated damages.
- In an action for breach, what is the manufacturer entitled to recover?
Answer: $75,000, because the enforceable liquidated damages clause fixes the exclusive remedy and is not reduced by the resale.
An enforceable liquidated damages clause displaces actual damages and is exclusive unless the contract says otherwise; here it expressly says sole remedy. The $75,000 amount was reasonable at formation. The manufacturer need not prove actual loss or mitigate because the clause substitutes for proof of loss. The resale proceeds are relevant only to actual damages, which are not recoverable. Therefore C is correct. A and B incorrectly reduce the liquidated amount by mitigation or resale. D is wrong because the duty to mitigate applies to claims for actual damages, not to enforcement of a valid liquidated damages clause.
- What is the likely result of the tenant's suit to recover the $300?
Answer: The landlord may keep only $10, because the $300 is an unenforceable penalty and the landlord may recover only actual damages.
A liquidated damages clause is enforceable only if the amount is reasonable in light of the anticipated loss and the difficulty of proving loss. Here the landlord's actual added cost was about $10, and the administrative cost of late payment was readily quantifiable; $300 is grossly disproportionate and therefore a penalty. The label 'liquidated damages' is not controlling. The landlord may recover its actual damages, but not the $300 fee. A and B incorrectly defer to the label. C is wrong because there is no rule that a late fee becomes valid only after 30 days.