Expectation interest - Next Generation Bar Exam
- What is the usual measure of a buyer's damages when a seller of land fails to convey?
- The difference between the market value and the contract price at the time set for performance. Incidental damages, such as costs of examining title, may also be recovered.
- What are incidental damages?
- Costs reasonably incurred in responding to the breach, such as inspecting, storing, or arranging substitutes. They are recoverable in addition to the loss in value of the promised performance.
- What position do expectation damages seek to place the nonbreaching party in?
- The position it would have occupied had the contract been performed. Expectation is the default measure of contract damages.
- When are nominal damages awarded for breach of contract?
- When a breach is proved but the plaintiff shows no actual loss. Nominal damages vindicate the right that was violated.
- What does 'cost avoided' mean in calculating expectation damages?
- Expenses the injured party saves because it no longer has to perform. Those savings are subtracted so the injured party is not overcompensated.
- What is the measure of a builder's damages when the owner repudiates midway through construction?
- Lost profit plus costs already incurred, less any payments received. Equivalently, the contract price minus the cost the builder saves by not completing.
- A seller repudiates a contract to sell land for $300,000 when the land is worth $340,000 on the closing date. What is the buyer's expectation recovery?
- $40,000, plus any incidental damages. The buyer loses the $40,000 benefit of the bargain measured at the time for performance.
- What is the general formula for expectation damages?
- Loss in value plus other loss, minus cost avoided and loss avoided. Other loss includes incidental and consequential damages; cost and loss avoided reflect savings from not performing.
- What is the usual measure of an owner's damages when a builder's performance is defective or incomplete?
- The reasonable cost of completion or repair. Courts substitute diminution in value when the cost of repair is clearly disproportionate to the benefit.
- A builder installs pipe of equal quality but a different brand than specified, and replacing it would require demolishing finished walls. What is the owner's measure of damages?
- The diminution in value, which is likely nominal. Where the deviation is trivial and repair would be economically wasteful, courts use diminution in value rather than cost of repair.