During the 18-month development cycle for a new piece of project management software, the product manager approved numerous feature requests from the sales, marketing, and executive teams. The final product was feature-rich but delayed, over budget, and so complex that the core target market of small businesses found it unusable. This product failure is a direct result of a breakdown in which aspect of the development process?