PASSAGE
A company is developing its predetermined overhead rate for the upcoming year based on direct labor hours. Budgeted manufacturing overhead is $960,000, of which $360,000 is fixed. The remaining overhead is variable with respect to machine hours. The company plans to produce 100,000 units, with each unit requiring 1.5 machine hours and 0.8 direct labor hours.
What is the company's predetermined overhead rate per direct labor hour?