A bank approves a six-week project to analyze loan-application abandonment for one digital channel and two customer segments. After data preparation is complete, the sponsor asks the team to include branch applications, four additional segments, and a prescriptive recommendation engine. The sponsor says the delivery date cannot change.
What should the project manager do first?