Liquidated damages and penalties
Bar Exam · Flashcards · Application
BAR EXAM · FLASHCARDS
Card 1 of 2
0 got it
0 to review
Current
Got it
Still learning
Not seen
QUESTION
A construction contract sets damages of $500 for each day of delay, and the owner's expected rental loss is about $450 per day. On what ground is the clause enforceable?
Tap to flip before you grade