Coordination
Review

Learn how Revit's Coordination Review tool detects and resolves conflicts between linked models: keeping your multi-discipline BIM project synchronized and clash-free.

Autodesk Revit

What Is Coordination Review?

In a real-world BIM project, multiple disciplines (architectural, structural, MEP) each maintain their own Revit model. These models are connected through linked files. When someone changes an element in a linked model, your project needs to know about it.

Why Coordination Matters

★ Catch Conflicts Early
A structural column shifts 2 feet: your wall alignment is now wrong. Coordination Review flags this before construction.
★ Save Time and Cost
Fixing clashes in Revit costs minutes. Fixing them on-site costs thousands of dollars and weeks of delay.
★ Maintain Trust
Teams can work independently knowing the system will automatically alert them to cross-discipline impacts.

The Linked Model Ecosystem

Host Model (Your Project) Architectural Linked .rvt Structural Linked .rvt MEP Linked .rvt Civil / Site Linked .rvt

The Core Mechanism: Copy/Monitor

Before Coordination Review can work, you must first establish what to watch. Revit uses a feature called Copy/Monitor to create a monitored copy of elements from a linked model into your project.

1
Copy/Monitor creates a local copy of selected elements (levels, grids, columns, walls) from the linked model.
2
Revit establishes a persistent link between the original element and your copy.
3
When the original changes, Revit flags the discrepancy for your review.

Copy/Monitor vs. Coordination Review

Copy/Monitor Coordination Review
Purpose Set up the monitoring relationship Review flagged changes
When Used Once, during initial setup Repeatedly, after each reload
User Action Select elements to copy and monitor Accept, reject, or postpone changes
Analogy Subscribing to notifications Reading your inbox

Types of Changes Detected

→ Moved
An element changed position in the linked model. Your monitored copy is now out of alignment.
✕ Deleted
An element was removed from the linked model. Your copy still exists but has no counterpart.
★ Changed
A property was modified: type changed, elevation adjusted, or parameters updated.

The Workflow

1. Link Model Insert .rvt link 2. Copy/Monitor Select elements 3. Work Teams design 4. Reload Link Updated .rvt detected 5. Coordination Review Review flagged items 6. Resolve Accept / Reject Repeat as models evolve

How to Run Coordination Review

1
Collaborate tab → Coordinate panel → click Coordination Review, then select Use Current Project or a specific linked model.
2
Review the list of flagged changes. Each item shows the element, the change type, and a description.
3
Choose an action for each item: Accept, Reject, or Postpone.
4
Add comments to document why you made each decision: this creates an audit trail for the team.
5
Close the dialog. Accepted moves update your copy. Rejected items remain for further discussion.

The Three Response Actions

✓ Accept
You agree with the change. Revit updates your monitored copy to match the new state of the linked element.
✕ Reject
You disagree. Your copy stays as-is. The flag remains so the responsible team knows a conflict exists.
★ Postpone
You need more information. The item stays in the queue and will reappear next time you run Coordination Review.

Example 1: Grid Line Shift

Grid B (original) Grid B (moved) Shifted Your Wall Scenario: Structural moved Grid B by 3 feet. Action: Accept the change and update your wall alignment.

Example 2: Level Elevation Change

Level 2
EL \(14'\text{-}0''\)
Level 2 (new)
EL \(15'\text{-}6''\)
\(+1'\text{-}6''\)
Level 1 Roof Floor-to-floor height changes Affects stairs, ductwork, piping

Example 3: Column Deleted

A B 1 2 B-1: DELETED Structural removed this column Your beam

What Can Be Monitored?

Levels
Floor elevations shared across all disciplines. Most commonly monitored element.
Grids
Column grid lines that define the building's structural layout and spatial organization.
Columns
Structural columns that walls, beams, and MEP routes must coordinate around.
Walls
Walls shared between architectural and structural models (e.g., shear walls).

Common Mistakes

✕ Never Running Review
Linking a model without ever checking Coordination Review defeats the entire purpose. Schedule regular reviews.
✕ Accepting Everything Blindly
Auto-accepting all changes without reading them can propagate errors into your model. Always read the description.
✕ Skipping Copy/Monitor
Coordination Review only works on elements you Copy/Monitored first. If you skip setup, nothing gets flagged.

Summary at a Glance

Concept Key Detail
Purpose Track changes in linked models
Prerequisite Copy/Monitor must be set up first
Location Collaborate tab → Coordinate panel
Change Types Moved, Deleted, Changed
Actions Accept, Reject, Postpone
Best Practice Run after every link reload
Most Monitored Levels and Grids

Question 1 of 5

What must be set up before Coordination Review can detect changes in a linked model?

Question 2 of 5

A structural engineer deletes a column from their linked model. When you run Coordination Review, what should you do if your beam depends on that column?

Question 3 of 5

Which of the following change types is NOT detected by Coordination Review?

Question 4 of 5

Where in Revit do you access the Coordination Review tool?

Question 5 of 5

Which elements are most commonly Copy/Monitored across disciplines in a BIM project?